IPC-A-620 is the industry-consensus acceptance standard for cable and wire harness assemblies. WHMA calls it the only industry-consensus international standard for the performance and acceptance of cable and wire harness assemblies. Specifying “build to IPC-A-620 Class 2” on a drawing is common, but that line produces a consistent verdict only when both parties share an understanding of scope, class and inspection plan. Most acceptance disputes we have traced start with an unnamed class, an unnamed revision, or inspection items never assigned to a station.
Below are the practical questions. What does the standard cover? Where does it end and IPC-A-610 begin? How are the three classes set, how are acceptance criteria written, and how are the open parts closed in an inspection plan?
What IPC-A-620 Actually Covers
Pairing illustrations with measurable requirements at each process step is how IPC-A-620 defines acceptable work. WHMA notes that OEMs and EMS providers use it as a foundation for requirements flowdown. That is why a buyer and a supplier can examine the same harness and still agree on what “acceptable” means, without either side inventing a private definition.
Covered ground runs from wire preparation, crimping, soldering and splicing through connector assembly, shield termination, marking, lacing and final electrical test. In particular, one assembly judged on two different benches should reach the same conclusion. That is the point of a consensus standard: the verdict does not depend on which shop built the part.
Scope deserves equal weight here. IPC-A-620 governs workmanship and acceptance, not electrical or mechanical design. Conductor gauge, shield grounding and routing belong on the drawing and in the design specification. Inspectors judge whether the crimp, the solder joint and the marking match that drawing once the build is done. We do not use it as a design manual.
WHMA also states that the standard provides acceptance requirements engineers can reference during product development, and that it supports reverse engineering and evaluation of harnesses. Its value therefore begins before production, not at final inspection.
IPC-A-620 vs IPC-A-610: Where Each Applies
Both standards sit in the IPC system, and both define acceptable conditions in three classes. By contrast, they do not judge the same object:
- IPC-A-610 addresses printed board assemblies, meaning solder joints and components on the board.
- IPC-A-620 addresses cable and wire harness assemblies, meaning conductors, terminals, connectors and jacket.
One product normally contains both. Boards carry components; harnesses link them to the rest of the system. Decide which standard applies to the item before judging it. We do not apply A-610 to a crimp barrel, or A-620 to a board-level joint.
| Dimension | IPC-A-610 | IPC-A-620 |
| Object judged | Printed board assembly | Cable and wire harness assembly |
| Scope | Solder joints, components, board surface | Wire prep, crimp, connector, shielding, marking, electrical test |
| Classes | Class 1 / 2 / 3 | Class 1 / 2 / 3 |
| Common misuse | Judging a crimp termination | Judging a board-level solder joint |
The Three Classes in IPC-A-620
Customers select the class on the drawing or purchase order, and a higher class tightens the acceptance tolerance.
| Class | Имя | Typical application | Acceptance posture |
| 1 | General electronic products | Consumer items, function first, modest service life | Widest tolerance; function is the gate |
| 2 | Dedicated service products | Industrial control, telecom, non-safety automotive | Extended life expected; quality balanced against cost |
| 3 | High-performance / high-reliability | Aerospace, defence, safety-critical automotive | Tightest tolerance; downtime and harsh environments excluded |
We would not present Class 3 as simply better. Its strictness carries a cost: process control, inspection and rework requirements all tighten with it. A general industrial controller inspected to Class 3 rarely justifies the spend. A safety-related part released to Class 2 may carry a risk that surfaces later. Class follows the intended use and the contract, not a reflexive choice of the highest number.
Class 1 does not license failure. Its tolerance is widest, but the floor remains functional reliability. Reading Class 1 as lower requirements is the most common misreading of the scheme.
How IPC-A-620 Defines Acceptance
IPC-A-620 breaks each process into conditions an inspector can compare: target, acceptable, defect, and the process indicator that signals a process starting to drift.
Take a crimp. Continuity is not the only check. Crimp height, bellmouth, wire brush length, insulation support position and conductor visibility through the inspection window are judged separately, so a row of terminations that look alike can hold a target, an acceptable and a defect condition side by side.
Soldering, splicing, insulation displacement connections (IDC), ultrasonic welding, connector insertion, shield termination and marking each carry their own set of conditions. Photographs do more work than prose here, because many of these judgements are visual and an image states the case more precisely than a sentence.
One point needs stating plainly. What the standard supplies is a criterion, not the sampling plan. It defines what acceptable means, but it does not say how many pieces to pull from a lot or how often to measure crimp height. That belongs in the inspection plan.
IPC-A-620 Does Not Set Inspection Frequency
People often miss this distinction. Build to A-620 answers the question of criteria; it does not answer the question of inspection coverage.
An inspection plan usually has three layers, and the cadence for each one is set outside the standard. First article confirmation puts drawing, material, tooling and test program on one build. Process audit brings periodic crimp-height measurement and die-life counting. Final inspection covers continuity and appearance. None of those frequencies comes from IPC-A-620; the purchase order and the controlled plan supply them.
We tie those three layers to our first article inspection routine: drawing revision, terminal part number, wire lot, die number and test-program revision all go into the record, so an anomaly can be traced to the individual build. At the incoming end, incoming quality control closes the loop. Wrong wire or wrong terminal cannot be recovered by a sharper final criterion. That is what requirements flowdown means in practice: the customer requirement has to become a task on a bench, not a line in a specification.
At final inspection we take the stricter route. Harness assemblies get 100% continuity testing and a mechanical pull test rather than a sample. Continuity checks the circuit relationships. Pull force checks the terminal-to-wire bond. They catch different defects. As covered in wire harness vs cable assembly, an assembly should not rest on a single spot check.
Who IPC-A-620 Certifies
Another term needs cleaning up. Strictly, A-620 certifies people, not factories. Specifically, inspectors and operators who pass an authorised training centre assessment receive the relevant qualification, commonly referred to as CIT or CIS. That distinction matters when a supplier claims the certification.
What a factory can certify is its quality management system: ISO 9001, IATF 16949 for automotive, AS9100 for aerospace. These two things answer different questions. System certification defines how process control, documentation, training and traceability operate, while A-620 defines what a conforming assembly must look like and measure. Capable shops run a certified system and staff it with operators and inspectors trained to A-620, but a system certificate is not proof of building to Class 3. We would not accept it as such.
That division carries into system integration. In PCBA box build, a harness is judged to A-620 before it enters the enclosure. Board-level work is judged to IPC-A-610 Class 3, and test methods follow PCB testing methods. Do not mix standards at the interface.
Four Questions About IPC-A-620
What Is the Difference Between A-620 and A-610?
A-610 judges solder joints and components on a printed board assembly. A-620 judges conductors, terminals and connectors in a cable or harness assembly. Different objects, different criteria. A single product usually needs both, applied to the right item.
Is Class 3 Better Than Class 2?
Class 3 carries tighter acceptance tolerance and a higher cost. It fits high-reliability, no-downtime applications, but for a general industrial assembly it rarely pays for itself. Select the class from the product requirement. Do not default to the larger number.
Why Is “Build to IPC-A-620” Not Enough?
Such a line omits three things: the revision, the product class and the inspection plan, meaning items and frequency. Without them, buyer and supplier hold different definitions of acceptable, and that gap usually shows up at incoming inspection.
How Is a Standard Revision Applied?
Revisions follow a multi-year cycle. Inspection uses the revision named on the drawing or purchase order. If the contract names an older revision, that revision governs. Changing it requires an engineering change, not a quiet substitution at the test bench.
Acceptance Is a Shared Language
Common language for judging a harness is the real value of A-620. Nothing in the standard fixes the revision, the class or the inspection plan, so those have to be written into the drawing and the order before work starts.
When citing IPC-A-620, name the revision and the class together, and define the inspection items and frequency for each layer of the plan. Those three pieces of information are therefore what keep a verdict from being argued at the receiving bench.